Second Floor Board Room
Richard J. Daley Center
50 West Washington Street
Board Material
Board Actions
| Task Order Awarded | |
| Project: | Charles R. Henderson Elementary School Renovation |
| Company: | Carnow Conibear and Assoc., Ltd. |
| Task Order Number: | PS2060D-001 |
| Task Order Amount: | $4,930.00 |
| Notes: | Environmental Engineering |
| Task Order Awarded | |
| Project: | South Side High School |
| Company: | Terracon Consultants, Inc. |
| Task Order Number: | PS2065G-001 |
| Task Order Amount: | $259,735.00 |
| Notes: | Material Testing |
| Task Order Awarded | |
| Project: | Esmond Elementary School Annex |
| Company: | ONYX Architectural Services, INc. |
| Task Order Number: | PS2088-004 |
| Task Order Amount: | $15,526.00 |
| Notes: | AOR Services |
| Task Order Awarded | |
| Project: | Read Dunning Salt Storage Structure |
| Company: | STL Architects, Inc. |
| Task Order Number: | PS3002-001 |
| Task Order Amount: | $513,311.88 |
| Notes: | AOR Services |
| Professional Services Contract | |
| Service: | Property Management Services |
| Project: | Richard J. Daley Center |
| Company: | MB Real Estate Services, LLC |
| Contract Number: | |
| Contract Amount: | |
| Notes: | |
| Contract Amendment | |
| Project: | Minnie Mars Jamieson Elementary School Annex |
| Company: | Architrave, Ltd. |
| Amendment Number: | PS2040-005 |
| Amendment Amount: | $1,395.00 |
| Notes: | Architect of Record |
| Change Order Approved | |
| Project: | Read Dunning School – site prep |
| Contractor: | K.R. Miller Contractors, Inc. |
| Contract Number: | C1586 |
| Change Order Amount: | ($29,810.37) |
| Reason for Change Order: | Other |
| Notes: | Deduct unused contingency |
| Change Order Approved | |
| Project: | Albany Park Branch Library |
| Contractor: | Wight and Company |
| Contract Number: | C1550 |
| Change Order Amount: | ($80,408.80) |
| Reason for Change Order: | Other |
| Notes: | Deduct unused site work allowance |
| Approval of Undertaking Request | |
| Project: | South Side High School |
| Details: | Undertaking Request from the Board of Education for the South Side High School Project |
| Other Action | |
| Action: | Name Change |
| Company: | Wood Environment and Infrastructure Solutions |
| Amount: | |
| Details: | Former name: Amec Foster Wheeler Environment & Infrastructure, Inc. |
| Other Action | |
| Action: | Name Change |
| Company: | ATC Group Services, LLC |
| Amount: | |
| Details: | Former name: ATC Group Services, Inc. dba Cardno |
| Other Action | |
| Action: | Name Change |
| Company: | Opidis |
| Amount: | |
| Details: | Former name: Mclaren Software |
| Other Action | |
| Action: | Name Change |
| Company: | OBrien and Gere Engineers, Inc. |
| Amount: | |
| Details: | Former name: Natural Resource Technology |
| Other Action | |
| Action: | Name Change |
| Company: | V3 Companies, Ltd. |
| Amount: | |
| Details: | Former name: V3 Companies of Illinois, Ltd. |
| Other Action | |
| Action: | Formulation Request |
| Company: | |
| Amount: | |
| Details: | Approval of a Request from the Board of Education for various school projects. |
| Other Action | |
| Action: | Report regarding the Interim Guaranteed Maximum Price (GMP) agreement for Design-Build services for the Richard J. Daley College Engineering and Advanced Manufacturing Center Project |
| Company: | Old Veteran Construction, Inc. |
| Amount: | Interim GMP (Amendment #2) $36,239,871.89 |
| Details: | Daley College Engineering and Advanced Manufacturing Center |